Re-tiling Project

Indoor Pool Re-tiling Project

Council is undertaking a rectification project to replace the indoor flooring with anti-slip tiles and fix minor drainage issues. This includes the change rooms, toilets and pool surrounds. As with all major refurbishment projects, there will be some inconvenience to pool users while the works are undertaken. The Oasis Management appreciates your patience and understanding while these works are underway.

How will it improve the Oasis?
The highest grade slip resistant tiles, which comply with Australian standards, will ensure people are safe when walking around the indoor pool complex.

Additional drainage grates will be installed throughout the poolside area and change rooms to improve drainage and prevent localised water pooling.

Tiling will be undertaken in stages until September, during this time swimmers are asked to take note of out-of-bounds areas.

Session 2 swimming lessons run from Monday 27th May- Sunday 18th August. During this time we will have access points to all pools, however please note the change rooms will be closed until 24th June. We have portable change rooms outside next to the 25m pool, access to Bolton Park change rooms and pop-up change rooms within the pool hall. We advise to bring children ready and dressed for their swimming lessons and wrap them up and take them home to shower as there are limited toilets, showers and change areas.
*Please note Monday lessons will be 9 weeks due to the 10th June 2019 public holiday 

Key dates:
Start date: 22 April 2019
22 April:
toilets and change rooms shut. Temporary toilets and change rooms in use.
29 April – 20 May: indoor pool complex shut. Outdoor pool open, weather permitting.
20 May: Indoor pools reopen. Floor tiling in progress until September.
24 June: Toilets and change rooms re-open.
Mid-September: Project completion.
End date: September 2019